Below is a ChatGPT generated summary of the 1879 specifications for the jail and sheriff's residence.
Introduction
This report outlines the construction specifications for a jail building in Seneca, Nemaha County, Kansas. The structure will include the jailor's residence, a female cell, an insane cell, and a large cell room. The following detailed descriptions highlight the necessary work and materials for the project based on the provided specifications and accompanying drawings.
General Description
The building will be constructed using brick with a stone foundation and will include a cellar under the jailor's residence. The structure will be two stories high, with the cell room being a single-story addition. The front dimensions of the building will be 31 feet 8 inches, with a total depth of 41 feet 1 inch and 51 feet 11 inches.
Excavation
The earth will be excavated to accommodate the foundation walls, footings, and cellar formations.
Excavation will also include digging holes for a cistern and cesspool as directed by the commissioners or superintendent.
Excess earth and rubbish will be removed from the premises, and the bottom of all trenches will be leveled for footing courses.
Masonry
The foundation stones will be high-quality limestone, laid in lime and sand mortar.
Footing courses will be 8 inches thick and progressively wider, with three courses for all walls.
Foundation walls will be built to specifications shown in the plans, with rubble work up to ground level, ensuring stones are laid on their natural bed and well-bonded.
Range Work
Above-ground stonework will be laid in regular courses ranging from 8 to 12 inches in thickness, with pitched faces and neat joints.
Window sills will be 5 inches by 9 inches, with door sills measuring 15 inches wide, both bush-hammered.
Concrete
The cell floors will have a concrete layer composed of spackle and mortar, thoroughly mixed with a ratio of 1/3 cement.
Window Sills and Doors
Windows throughout will have box frames with sash, weights, and cords, featuring 1 3/8-inch thick sash.
Door sills will be 6 inches longer than the width of the opening, with a 5/8-inch bevel cut, and steps will be bush-hammered.
Brick Work
All bricks will be well-burned and merchantable, with exterior bricks uniformly dark red.
The cell room will have hollow walls bonded with headers every sixth course, ensuring no joint exceeds 3/8 inch in width.
Brick layers will set necessary tiling flues and construct a cesspool lined with 9-inch brick.
Carpenter Work
Includes framing and setting stakes and centers, with all joists, ceiling joists, trimmers, lintels, and rafters specified for dimensions and spacing.
The portico will feature 10-inch by 10-inch posts with molded caps and bases, and a ceiling of tongue-and-groove pine.
Plastering
Ceilings in the residence and cells will be lathed with seasoned pine and receive two coats of brown mortar, with a third coat of plaster of Paris.
Galvanized Iron and Tin Work
The residence will have a galvanized iron cornice, with the roof covered in 1X roofing plated tin, including gutters and downspouts.
Cistern
The cistern will be 8 feet in diameter and 11 feet deep, lined with 9-inch brick walls and a concrete-coated arch, connected to an overflow pipe.
Windows and Doors
Windows in the residence and cells will have box frames with sashes, pulleys, weights, and cords. Doors will be four-panel, with exterior doors being 1 5/8 inches thick and interior doors 1 1/8 inches thick.
Hardware and Finish
All doors will be hung on bolts and secured with locks, with hardware furnished as required.
Interior finishes include plain 6-inch casings with 8-inch base moldings, and floors laid with 7/8-inch flooring boards.
Stairs
Cellar stairs will have open risers and plank treads, while the main stairs will feature turned balusters and handrails.
Painting and Glass
All tin work will receive a coat of paint, and interior woodwork will have three coats of lead paint. Glass will be of the best quality, well bedded and trimmed.
Plumbing
A 6-inch vitrified clay pipe will run from the kitchen and cells to the cesspool, ensuring proper drainage.
General Conditions
Any necessary additions, alterations, or substitutions will be consented to by the contractor and must be approved by the superintendent.
The contractor will provide all labor and materials needed to complete the building by the specified date, ensuring all elements are built to specification.
Conclusion
The specifications detailed above provide a comprehensive guide for the construction of the jail and residence in Seneca, Kansas. All work must be completed to the highest standards, ensuring durability, safety, and compliance with the architectural plans and elevations.
The Nemaha County Historical Society has a photocopy of the 1879 contract with P. J. Pauly to build a new jail.
CONTRACT, Made this 3d day of June A.D. 1879, between P. J. PAULY & BRO., of St. Louis, Missouri, through their Agents, C.L. WUNDT & CO., of Burlington, Iowa, of the first part, and the County of Nemaha in the State of Kansas by the Board of County Commissioners thereof, party of the second part, WITNESSETH: That for the consideration hereinafter named, and agreed to be paid by the party of the second part, the said party of the first part agrees to manufacture and erect in the Cell Room of the Jail building in the Town of Seneca in the County of Nemaha and State of Kansas, Three Cells finished complete, ready for occupancy, including all the attachments connected therewith, in accordance with the Specifications hereto attached, marked "Exhibit A;" and also manufacture and furnish for the use of said party of the second part, 4 Doors, and 9 Windows Guards as per Specifications hereto attached, marked "Exhibit B." And also build the building according to plans and specifications hereto attached marked Exhibit C And the said party of the first part agrees to take and accept the sum of Nine Thousand Nine hundred and forty three Dollars in Cash. in full payment for said cells building & iron work the freight and drayage on said Cells to be paid by the party of the second art, and deducted from the amount paid to the said first party on final settlement. The said party of the second part, hereby accepts the foregoing contract and for the manufacture and erection of said Jail Cells and the furnishing of said Iron Work and the erection of said building hereby agrees to pay to the said party of the first part or order, the sum of Nine Thousand Nine hundred and forty three Dollars
page 2 in full thereof. It is further agreed by and between the said parties hereto, that the work on said Cells Building & Iron Work is to be commenced on or before 20 days from this date and completed on or before the 1st day of October 187? The said party of the 1st part agrees to furnish 7 bars of old railroad iron, each 12 1/2 feet long to set said Cells on, and when notice of the time fixed for the completion thereof is given by the said party of the first party, the said Board of County Commissioners shall convene in special session at a time to be fixed by the said party of the first part, examine the said work, and if completed according to contract, shall accept the same and make payment therefor as hereinbefore agreed. In Testimony Whereof, he said party of the first part, has cuased this to be signed by the said C. L. Wundt & Co., Agents, and the said party of the second part has caused it to be signed by the members of the Board of County Commissioners and attested by the signature and official seal of the County Clerk of said COunty, this 3rd day of June A.D. 1879 P. G. Pauly & Bro by C. L Wundt & CO Agents
A. H. Burnett T M Durland G H Adams Members of the Board of County Commissioners of Nemaha County, Kansas
The Nemaha County Historical Society has a photocopy of the 1879 bond for the P. J. Pauly contract to build a jail in Nemaha County.
Nemaha County Commissioners
Bond
Whereas a proposition has this day been made whereby Messr P. J. Pauly & Bro of St. Louis, Mo., by C. L. Wundt & CO., their authorized agents are to [in- dulata] the erection and completion of a Jail Building & Cells within and for the county of Nemaha in the state of Kansas, according to the plans and specifications accompany ing said proposition. Now therefore, know all men by these presents that we the aforesaid P. J. Paul & Bro. as principals and C. L. Wundt & Co., S. T. [Acres], E. C. Blackman, J. Cullaton and R. R. Dorr as sureties are held and firmly bound unto the said Nemaha County Kansas in the penal sum or Twenty Thousand Dollars ($20,000.00) for the payment of which will and truly to be made we hereby bind ourselves our heirs and assigns firmly by these presents.
The condition of the above obligation is such that in the event that the contract for the erection of the aforesaid Jail Building and Cells in accordance with the plans and specifications above referred to shall be awarded to the said P. J. Pauly & Bro in the times states in the proposition herewith filed, the said P. J. Pauly & Bro
shall and will faithfully comply with all the stipulation and con ditions named and set forth in said specifications and contract, and erect and complete said Jail Building & Cells in full com pliance and accordance therewith Then and in that case, this obliga tion to be null and void, otherwise to be and remain in full force and virtue in law. P. J. Pauly & Bro By C. L. Wundt & Co Agts C. L. Wundt & Co.
S. T Acres E. C. Blackman J. Cullaton R. R. Dorr
State of Iowa, Des Moines County, SS: The undersigned, sureties for P. J. Pauly & Bro whose names are signed to the foregoing Bond, being duly sworn, do severally depose and say as follows: I, S. T. Acres do say that I am a resident of the State of Iowa, and that I am worth the sum of Five Thousand Dollars beyond the amount of my debts, and have property liable to execution in this State equal tot he sum of Five Thousand Dollars. I, E. C. Blackman do say that I am a resident of the State of Iowa, and that I am worth the sum of Five Thousand Dollars, beyond the amount of my debts, and have property liable to execution in this State equal to the sum of Five Thousand Dollars S. L. Acres E. C. Blackman Subscribed and sworn to by the said S. T. Acres and E. C. Blackman before me this 21st day of May 1879 T G Foster Notary Public
Approved I, J Cullaton do say that I am a resident of the State of Iowa, and that I am worth the sum of Five Thousand Dollars beyond the amount of my debts, and have property liable to execution in this state equal to the sum of Five Thousand Dollars I, R. R. Dorr do say that I am a resident of the State of Iowa, and that I am worth the sum of Five Thousand Dollars, beyond the amount of my debts, and have property liable to execution in this State equal tot he sum of Five Thousand Dollars J Cullaton R. R. Dorr Subscribed and sworn to by the said J Cullaton and R. R. Dorr before me this 21st day of May 1879 T G Foster Notary Public
Bond of P. J Pauly and Bto and others conditioned to the faithful performance of the contract for the erection and com pletion of jail Filed June 3, 1879 Joshua Mitchell County Clerk The within Bond and the sufficiency thereof approved this 3d day of June AD 1879 By order of the Board of Commiss ioners A H Burnett Chairman
The Nemaha County Historical Society has a photocopy of the original 1879 specifications for the jail cells to be provided by P. J. Pauly & Bro.
[EXHIBIT A] SPECIFICATIONS For Three Steel-Clad Jail Cells & Corridor, To be Constructed under the direction of P. J. PAULY, and erected in the Cell Room of the County Jail at Seneca in Nemaha County, Kansas By P. J. PAULY & BRO., of St. Louis, Missouri, As per Contract hereto attached. THE PATENTS COVER THE FOLLOWING ITEMS: FIRST.—The hardened Steel Bars, with annealed and iron centre, (saw and file proof) and the process of hardening. SECOND.—The lathing of the Iron with hardened Steel Bars. THIRD.—The Lever Lock. PLATE WORK. Each Cell to be 6 1/2 feet wide, 8 feet deep, from front to rear, and Seven feet high. The Corridor to be five feet wide, 19 1/2 feet long, and 7 feet high. The floors and ceilings of Cells and Corridor, and the outside and partition walls of Cells, and the rear end of Corridor, and 8 inches of the front end of the Corridor, where the Lever Box is attached, to be made of 3/16 inch thick Jail plate. All the joints to butt, and to be strapped with a 4 b 1/4 inch Iron Strap, thus [image1] All the inside corners are put together with a 2 by 2 by 1/4 inch angle iron, thus: [image2] and all the outside corners to have double angle iron, thus: [image3]Outside angle Iron to be 2 1/2 by 2 1/2 by 1/4 inches. All to be riveted with [3/8] inch counter- sunk oval head rivets, and counter-sunk riveted on the inside. Rivets to be spaced from 3 to 3 1/2 inches from centres.
LATHING. All the exterior plate Iron of Cells and Corridor to be lathed with the patent hardened steel bars, hardened on the edges, and annealed in the centre. The bars to be 2 by ⅜ inches, placed 5 to 5 1/4 inches apart, and the ends to extend in under the outside angle Iron, and riveted every 6 inches with 1/2 inch counter-sunk oval head rivets, counter sunk riveted in the plate. STEEL LATTICE WORK. At the end of each Cell there will be a lattice section, (or window,) 2 feet wide, extending from floor to ceiling, to admit air and light—made of the patent hardened steel bars 2 by 2 inches, crossing at right angles, and the ends to be riveted at every intersection with 1/2 inch counter-sunk oval head rivets, counter sunk riveted on the inside. Meshes to be 2½ by 2½ inches. Said lattice section is riveted at top and bottom, between the outside and inside angle Iron, and on the sides to be securely riveted to the plate. CELL DOORS. Each Cell to have a door 2 feet wide, and 6 feet high, made of same kind of material, and constructed in the same manner as the rear sections hereinafter described and at the bottom there will be a feed opening 4 1/2 by 6 1/2 inches. Each door will be hung on a pivot of double strap hinges thus: [image4] Protected by hardened steel bars, and opposite each hinge on the door will be a hardened steel rabbit catch, which will shut into a mortise in the angle Iron frame, thus: [image5] In the center, across each door, will be a 4 by 3/8 inch patent hardened steel latch-bar, riveted to the door with a double row of rivets. Each door-opening will be provided with a 2 by 2 by 1/4 inch angle Iron frame securely riveted to the plate on the inside, and forming a rabbit for the door to shut against.
CORRIDOR GRATING The entire front, and the entrance end of the corridor, (with the exception of 8 inches, where the Lever Box is attached) will be made of the patent hardened steel bars 2 by 3/8 inch, crossing at right angles, and to be riveted at each intersection with 1/2 inch counter-sunk oval head rivets, counter-sunk riveted on the inside. Meshes to be about 3 by 4 1/2 inches. This latticework is secured at the top and bottom, and at all the upright corners, with double angle Iron, and riveted with 1/2 inch rivets, (As above described), passing through both thicknesses of the angle Iron, with the steel bars between them. The inside angle Iron to be 2 by 2 by 1/4 inches; the outside 2 1/2 by 2 1/2 by 5/16 inches. The several sections of the steel lattice work of the Corridor are connected at the joints, by placing a 4 by 3/8 inch patent hardened steel bar on one side, and a 4 by 3/8 inch Iron bar on the opposite side, riveted through both bars, with the ends of the lattice bars between them, with a double row of 1/2 inch rivets, in same manner as hereinbefore described.
CORRIDOR DOOR The entrance door to the Corridor will be made of steel lattice work of same kind of material, and in same manner as the Corridor lattice work above described, and will be 2 feet 6 inches wide, and 7 feet high. Each side of the door will be stiffened by an angle Iron bar, 2 by 2 by 1/4 inch, riveted to the door on the inside. The door will be hung in the same manner as the Cell doors hereinbefore described. On the outside of the door there will be a 3/16 inch thick Iron plate, about 15 by 20 inches, securely riveted to the door : on which will be riveted a heavy slide bolt made of hardened steel and iron combined. Said bolt slides into the Lever Box, (hereinafter described,) and is secured there by a heavy pad- lock. Another slide bolt will be secured to the front of the Cell plate. This bolt slides over the edge of the door, and securely fastens it at the bottom. This latter bolt is locked with a heavy pad-lock on the Cell side, and out of reach from the inside.
IMAGE 1Image 2Image 3Image 4Image 5
LOCKING ARRANGEMENTS Each Cell door to be locked by means of P. J. Pauly’s Patent Lever Lock, which locks the door at the top and bottom with heavy bolts. The lever controlling this lock is locked into an Iron box, made of 3/16 inch thick Jail plate, secured to the plate on the front end of the Corridor, adjoining the entrance door. The door to thus Lever Box to be secured with a live tumbler wrought iron lock, with a combination to close key-hole with a plate. In addition to the above each Cell door will be provided with a heavy Jail padlock, placed on the steel latch-bar across the centre.
BUNKS. Each Cell will be provided with 4 sets of angle iron bunks, to swing hammocks from. Hammocks to be 28 inches wide, made of No. 4 Ducking, with 3/8 inch cord, sewed into edges all around and swung from side to side of cell. At each end there will be three heavy 1 1/2 inch leather straps and buckles to fasten the hammocks to the angle iron loops, which are riveted to the sides of the Cells. FOUL AIR DUCTS. In one corner of each Cell there will be a foul air duct, made of No. 14 plate Iron, and riveted to the Cell plate, as shown on the plan. They will have two shifters; the one at the bottom to be large enough to receive a night bucket, and the one at the top large enough for draft. The duct is connected with a6 inch Iron pipe on top of Cells, extend- ing through the ceiling over head. A 10 inch ventilating cap will also be placed on the roof of building.
WATER CLOSET There will be a Tank made of No. 14 Iron, 3 feet square and 2 feet deep, placed on top of the rear end of the Corridor. There will be a 1 inch supply pipe from the tank to the privy sink, with a globe valve for sink, and brass cock to supply drinking water. A cut-off cock will also be placed in said supply pipe on the outside, to regulate the supply of water. There will also be an over-flow pipe, and a supply pipe running from tank to outside of the building. WATER TANK There will be a tank made of NO. 14 Iron, 3 feet square and 2 feet deep, placed on top of the rear end of the Corridor. There will be a 1 inch supply pipe from the tank to the privy sink, with a globe valve for sink, and brass cock to supply drinking water. A cut-off cock will also be placed in said supply pipe on the outside, to regulate the supply of water. There will also be an over-flow pipe, and a supply pipe running from tank to outside of the building. PUMP AND HOSE A force pump, of an anti-freezing pattern, will be placed on the well or cistern, of sufficient capacity to carry water to the tank — the connection between the pump and supply pipe of the tank to be made by a 1 inch, 3 ply rubber hose Said hose to be 30 feet or less in length, and to have the proper couplings for attaching at each end. A nozzle for sprinkling and extinguishing of fires will also be furnished, to attach to said hose when required. PAINTING Said job will receive one coat of mineral paint before leaving the factor, and one additional coat after being set up in the Cell room. FINALLY All the above Iron and Steel work to be the best in every particular, and to be done to the entire satisfaction of The County Commissioners of Nemaha County, Kansas and in accordance with the contract, and the samples, model, plans, &c., exhibited by C. L. Wundt & Co. General northeaster agents of Burlington Iowa P J Pauly & Bro [for] C. L. Wundt & Co Gen Agents
NOTE: Portions of this document were nearly illegible. This transcription is a best effort but may contain errors.
1879 Jail and Residence Specifications
Specifications of work and material required in the construction of a Jail building consisting of Jailors residence Female Cell & Insane Cell, and large Cell Room to be erected in the city of Seneca County of Nemaha state of Kansas according to the specifications and accompanying drawings
General Description The bldg to be of brick with stone foundation. To have cellar under jailors residence only. Building to be 2 storys the Cell room to be one story. The entire front of bldg to be 31.”8” by a total depth of 41:1” 51:11” For furthere particulars refer to plans & elevations
Excavation All earth to be dug the necessary width and extent required to receive foundation walls footings for the formations of cellars area &ct For depth of cellars &c refer to plans & section Sufficient quantity of earth to be used in grading ground around the buldg as may be directed by the county commissioners or superintendent All superfluous earth to be carted away form premises also all other rubbish Bottom of all trenches for footing courses to be made perfectly level and of sufficient width to allow men
page 2 to work in easily There will be hole dug for cistern as may be directed also for cesspool as may be directed by commissioners or superintendent
Masonry All stone used in foundations &c. to be of the best quality of limestone. To be laid in best line and sand mortar. All footing courses to be 8” thick each source to be 12” wider than preceeding one There will be three courses to all walls. The courses for residence walls to be thus respectively 8” x 2’6”, 8” x 3’6” & 8” x 4’6: For the cellroom walls respectively 8” x 3’0”, 8” x 4’0” & 8” x 5’0” Bottom courses to be well bedded & every stone to extend to centre of wall. Top course stone of footing course to be through stone. All is to be laid on their natural [treds] in good line and sand mortar. All interstices to be well filled in with [spauls] and mortar. All foundation walls to be of size and hight as sown on plans and section. All walls up to level of ground to be of good [rubble[ work. No stone to be more on the] face than 1/3 the thickness of wall. Every stone to be laid on its natural bed. All interstices to be well filled in with spauls & mortar & well slashed joints both in & outside of walls. Every three feet there will be a through stone. All stone to be laid in good line and sand mortar. Arches to be sprung where shown all walls to be well bonded together to be guilt neat plumb & level
page 3 Range Work All stone work above ground to be laid in regular courses ranging form 8” to 12” in thickness and to be pitched faced with neat joints. All joints to be straight and plumb. The last course to have [was] cut on same thus 3” x 3” Stones to be neatly pitched off around openings. Last course of stone extending over basement windows to be 8” longer than width of opening to form cap. Mortar joints to be scraped out on outside & not to be more than 3/8” and neatly pointed in cement
Concrete To have [?] concrete under entire cells composed of [spackle] & mortar To be thoroughly mixed Mortar to be 1/3 cement. TO be good & substantial work.
Window Sills &c All the windows throughout to have 5” x 9” sills thus and to be 6” six inches longer than width of opening. The top of sill to have a wash or level cock on same of 3/8: & to be drove to be neatly bush hammered work Doors to have sills to be 6” six inches longer than width of opening the face to be same thickness as last course of range work. All doors sills to be bush hammered and a 5/8 bevel cut on same these sills to be 15” wide The steps on side to be made of stone to be 7” rise x 10” tread and as shown on plans and elevations All to be bush hammered work. All the above described cut stone work to be of the best stone that can be obtained in vicinity of bldg
page 4 To have proper beds for stone and cellar work to be neatly set. All corners to be full and square to flag stone to be allowed To have one large step, going from hall to cellroom To be of same material and workmanship as above work to be 7” x 15” x 3’6” all properly set.
Brick Work All brick through to be of best well burned merchantable brick. All brick to be laid in good line and and mortar The brick used for exterior work to be of uniform dark red & even color. All outside walls of Cell room to be hollow walls thus to be made of sizes as shown on plans. To be well bonded with headers every sixth course. Every sixth brick with heading course to be clipped out so as to [clair] pass into roof. In building the walls the 4 1/2 walls is to be built to the outside and the joints in hollow space to be s[et] flush also the inside of bldg. The outside work to be neatly pointed and no joint to exceed 3/*”in width Archers to be turned over all openings (on inside) to have proper lintles for all openings Wood brick to be put in where directed by carpenter Residence walls to be built as shown on plans elevations and section. All work to be neatly pointed and all exterior bricks to be of an even dark red color. All joints to be neatly struck. All walls to be carried up perfectly plumb and level. NO wall to be carried up more than one scaffold high
page 5 before the adjacent walls are carried Recesses to be left in wall for [soil] and supply pipes &etc. All brick through to be laid in good line and sand mortar and all to be thoroughly slushed and grouted Flues to be built where shown. Brick mason is to set & furnish tiling flue 10” diameter in the clear in the stack as shown. All flues topped out asper elevation The sockets of tiling flue to be well cemented and the pipes to be fastened with galvanized iron anchors This tiling pipe to be set inside of a square brick flue and brick flue to be free form obstruction. The inside of cell room to be flush jointed and well [rubbed]. This room will not be plastered. Cesspool to be 8’0” diam. by 10:0” deep and to be lined with 9” of brick laid dry. To be arched over top with 9” of brick laid in cement. To have 6” thick cap stone over same neatly dressed and to have a hole large enough on same to receive foul air shaft. All above described work to be done in the best and most workmanlike manner. Brick layer to furnish necessary 6” ch of iron [thin?] for all flues. Last three courses of brick on chimney to [pass] fire wall to be laid in good cement mortar. To have net [dental] brick cornice on jail room Bldg. as shown on elevation with stop block Cell room to be paved with best hard burnt brick laid flatwise on 2” of sand & well tampered. To have proper foundation for portico posts Brick contractor to set all ventilating grates furnished by iron contractor
page 6 Carpenter Work The carpenter is to furnish & set stakes centers & etc The carpenter work includes all and every kind of [?] work required in the construction of said bldg as shown on plans elevations and sections and according to these specifications or as may be directed by the superintendent
Timber and Framing All joists in first and second story to be 2” x 10” braced with [course] of [?] bridging 1” x 3” through the centre of each lien of joists. All joists to be spaced 16” from centres Ceiling joists to be 2” x 6” set 16” from centres. Trimmers for flues stairways and other purposes to be framed double thickness All lintels required to be made of 2”x6” spaced thoroughly together the required width to cover opening Cell room ceiling joists to be 2” x 6” All trimmer be well framed or spiked together as the case may be All the wall plates to be 2” x 8” and to be placed to [receive] all rafters Rafter [?] to be 2” x 6” placed 2 feet from centres and [?] spiked to wall plates [?] beam [?} to section for truss 8” x 10” rafter [?] Heels of truss to be [shorter] widt 3/4” [? Two of these as each heel to [?] [lo?ts] placed where required.
Roofs to be covered with such quality of pine sheathing [barriers] [there] [?bly} [secured[ ? to be laid [close] and [Seals] make of the [?] to rafters [?] board to be
page 7 over 10? in width all to be done in the best workmanlike manner
Portico For general descriptions of portico refer to plans and elevations posts to be 10” x 10” neatly moulded caps & bases Cornice as shown with bracket Posts to be chansfered Underside of portico to be covered with best quality pine of ceiling stuff laid close & level (tongue & grooved & secret nailed to every joist. All to be done in the most complete manner. Floor of portico to be of best tongue & grooved white pine flooring board 1” thick secret nailed to every joists Ceiling boards to be 7’* thick All to be thoroughly season free form loose knots sap & other imperfections Roof of portico to be covered with white pine sheathing board laid close & level Boards to be thoroughly season & free fro knots &c. slips of portico to be as shown on elevation & plans
Plastering All ceilings in first & second story of residence and female & insane cells to be lathed with best quality of throughly season white pine laths & to be done in a substantial and workmanlike manner all walls and ceiling of residence (excepting insane and female cells) to receive two coats of brown mortar put
page 8 true and level and finishing coat or 3d coat to be of plaster of paris well trowelled Female & insane cells to receive [?} coats of brown mortar last coat neatly floated off. All to be done in the most substantial and workmanlike manner All mortar to be of fresh burned lime and clean [?] sharp sand.
Galvanized Iron
The residence to be surmounted with [neat] galvonized iron cornice as shown on elevations To be made of half sheet galvanized iron free from buckles, knicks joints to be riveted with button head rivets. All corners to be cross lugged on inside cell then roughly soldered. No open joints allowed, & all to be fastened to their respective lookout. &c. To be done in the best workmanlike manner To have galvanized iron [?] under caps of up[stairs] [?] [pattern] for windows or [?]
Tin Work All roof of residence, jail bldg & portico to be covered with best quality of 1X roofing plated standing grooves and be well cleated and soldered. [Use] edges of collars [solderedence] to be thoroughly soldered. There will be an [O. J.] gutter placed on brick cornice of jail bldge to be well fastened with galvanized iron straps long three feet [?47} downspout to be 4. in diameter and placed as nature of work requires or as may be decided by superintendent to have all proper flashing
page 9 round chimneys walls etc to be done in the best manner Tinner to set ventilating caps with are furnished by iron contractor TO have small gutter & downspout for portico at on in same manner as others above described All win work to be of 1x tin to be done in best & most workmanlike manner [?] as may be directed by the superintendent. Ten roofing to receive one coat of [nine] paint on underside by [reshing laid]
Cistern To be constructed where directed. To be 8:0” dia and 1[1] ft deep top of arch to be 2 ft below grade line. To be laid up with 9” walls of extra hard burned brick laid in line and sand mortar cistern to be covered with 9” arch coating to be 1” thick of [concrete] mortar Bottom also in cement and amount to put on in tow coa[ts] to have [m?] &c and proper cap & holds &c To have overflow pipe to connect with 8” pipe. Described to be done in a [complete] manner and approv[al] by the superintendent.
Windows and Doors All windows throughout residence femal cell & insance included to be box frames, [draws] pulleys, sash and wights & cords Frames [a g mounts] and 1” thick last to be 8 [lights] 14: x 18” glass, 1 3/8” thick sash, [Legrund] lead frames
page 10 Casework windows to have 2” plank frames to be 2 lights and 14” x 18” glass Frames to cell room to be 2” plank frame to be south windows as shown each window to be lights 8” x 12” glass Sash to be 1 3/8” thick
Doors Outside doors to be 2:5” x 6:5” four panel [og] molded sails & styles. TO be 1 5/8 thick being to a 2” rshetted plank frame to have transoms above to bri[ng] with and hight as with windows. All inside soors to be 2:8” x 6:5” 1 1/8” thick four pane [?] and sytles. All to be hung to a [draftable] plank frame There will be a plain door leading from hall to cellar made to correspond with surrounding doors There will be a plain 2” plank folding door to coal sluice Doors to Female & Insane cells to be 2: x 6:0” 1 5/8” neat panel as above described doors.
Hardware All doors to be hung on [loose p?] bolts & secured with bet [strengthin] locks sash fastener for windows in residence and all hardware to be furnished as required to make bldg complete
Inside Finish For [?] windows and doors of residence to be plain 6: with og moulding to mitre with top mould of base around doors. Base to be through out to be 8” with mouldens on top to have plain stools
page 11 and aprons for windows. Cell room windows to be plain 1” x 6” casing bevelled edge. To have neat moulded panel between windows sink in kitchen to be boxed u neatly with [?atched] boards.
Flooring and Ceiling The entire floors throughout residence to be laid with 7/8” mill worked flooring boards well [spaced 2nd quality free from loose knots &c. and to be secret [sealed] to every joist The ceiling of cell room to be covered with 7/* tongued & groved ceiling stuff. 2nd quality well seasoned & secret to every joist. All lumber to be thoroughly seasoned free from loose knots & other imperfections The work to be done in the most workmanlike manner Side of in hall to be boarded with same stuff s ceiling mill worked boards done in a neat manner.
Stairs The cellar stairs to be open risers 2” plan tread to rest on two strong carriages to have plain [newel] post and hand rail. Stairs from 1st to 2nd story to have 7/8” riser & 1” thick tread to rest on two strong carriages to be not less than 4” at the weakest point treads to have nosings worked
page 12 [cellar stairs] into wall stringer and furnished with [?] Stairs to be surrounded with a plain 2” handrail 1 3/8” turned balisters with 1” [?] post. Rail and balisters to [?] 2nd story.
[?] and [?] [?] roofs, gutters [?] to be painted [and made] of [manners] [?] [?] work [?ualtly] painted to recive three coats of white lead in [?] linseed oil and of such tints as may be [?] by the superintendent [?] of white lead [?] put on thick
Glass all glass throughout to best [?] manner [?] and to be well bedded trimed and [back] putt[ied] [?[ to be [?] [?] or [fl?] one [?]
page 13 [?] There will be a 6” ventified clay pipe [?] from [/} kitchen, female & insane cells to so need with [?] pipe from rear of bldg which [in] [8”] to continue then to cess pool All pipes to be well laid with [a fall] of 3[?] to the foot [? ] of the [?] [?] All pipes to be good and sound [tread] All necessary T’s & elbows placed as here required.
General Conditions On case of any additions, abbreviations alterations of plans to specifications may be required having the construction of said bldg [license] shall be consented to by the contractor and carried into effect. The contractor is required to furnish perform & provide at his own cost & [?] all & every kind of labor and material to good sound quality & inspection required together with all goods and [cartage] loads tackle etc which may be necessary for the proper execution erection and completion into sound & workmanlike manner so as to carry out the plans eleva tions [?] drawings to the true [intended[ mean ing of this specification Also the same without [?] [?] to the county & delivery said bldg in as clear and [tensatable] conditions on or before the 16 day of __ 18 __ AD And anything not shown or specifications by aforesaid plans or specifications such as setting iron doors windows etc. to [?] to make the bldg complete in every particular. P. J. Pauly & Bro pr C. L. Wundt & Co General Agents
History of the Nemaha County Sheriff’s Residence and Jail
Written by ChatGPT from Newspaper articles June 2024
Early Plans and Construction
The history of the Nemaha County Sheriff’s Residence and Jail began in October 1878, when the Board of County Commissioners proposed the construction of a new jail. The Seneca Weekly Courier reported on October 11, 1878, that the board had ordered a vote on the matter, expressing confidence in the proposal’s success due to the county’s sound financial standing. By November 15, 1878, the Courier confirmed that the proposition had been overwhelmingly approved by a majority of 1,277 votes.
On June 3, 1879, the contract for building the jail was awarded to P. J. Pauley & Bro. for $9,943, as documented in the Seneca Weekly Courier on July 4, 1879. The steel-clad cells, a significant feature of the new jail, were installed in early September 1879. The Courier’s September 5, 1879, edition highlighted the advanced security and compact design of these cells.
Architectural Features and Early Use
By September 24, 1879, the jail’s construction was nearing completion. The Seneca Weekly Courier described the building as a brick structure with a two-story front and an “L” extension for the jail cells. Measuring 32×20 feet, the main building contained six rooms, while the “L” section, sized at 22×20 feet, housed three steel cells based on Pauly’s patent. These cells were praised for their security and sanitary features.
The Nemaha County Jail was formally received by the commissioners on October 9, 1879. The Seneca Tribune detailed the sophisticated design of the cells, which were constructed to be escape-proof and sanitary. The cells featured a lever system that allowed the jailer to operate the locks without direct contact with the prisoners, enhancing security.
Early Incidents and Jail Breaks
Despite its advanced design, the jail experienced several escape incidents. On February 26, 1904, the Courier Democrat reported that a prisoner named Henderson escaped by digging through the brick wall while the sheriff was away. Henderson’s escape was significant enough to warrant the use of bloodhounds for tracking, though he ultimately eluded capture.
Further escape attempts continued, with notable incidents on August 23, 1906, and August 30, 1906, where prisoners Joe King and Thompson escaped through the roof. These incidents underscored the need for a more secure facility.
Plans for a New Jail
By April 12, 1906, discussions about constructing a new jail had begun. The Courier Democrat mentioned that the current jail was not only insecure but also unsanitary. The county commissioners, with guidance from legal counsel, decided they had the authority to build a new jail without a public vote. Plans were drawn by the Pauly Jail Building Company, envisioning a two-story structure with modern facilities.
The bidding process for the new jail construction began on April 18, 1907, and concluded with the award announcement on May 23, 1907. Construction culminated in December 1907, with Sheriff Dennis moving into the new facility, which combined modern amenities with enhanced security features.
Mid-20th Century Renovations
By January 13, 1955, the Courier Tribune reported that the jail residence was undergoing repairs and redecoration, highlighting structural issues with the south wall supporting the cupola. On April 7, 1955, the Courier Tribune detailed the removal of the heavy cupola and the rebuilding of the south wall to address these structural problems.
Conclusion
The Nemaha County Sheriff’s Residence and Jail, from its initial construction in 1879 to its significant renovations in the mid-20th century, reflects the evolving standards and needs of county law enforcement facilities. Despite early challenges with security and structural integrity, the county’s commitment to maintaining a secure and modern jail has been evident throughout its history.
The History of the Nemaha County Jail as told by newspaper accounts.
October 1878
The Board of County Commissioners have ordered that the people vote this fall whether they want a new jail in Nemaha county. We don’t know of any one opposed to building one, and expect to see the proposition carried unanimously. We are well fixed financially, and now is the time to build.
Seneca Weekly Courier – 11 Oct 1878, page 4
15 Nov 1878
It is very evident the people of Nemaha county want a new jail— the vote having carried by 1,277 majority.
Seneca Weekly Courier – 15 Nov 1878, page 8
4 July 1879
Abstract of the proceedings had by the Board of Commissioners of Nemaha county, Kansas, sitting as a Board of Equalization at a meeting of said Board begun on June 2, 1879, and adjourned on Tuesday, June 17, 1879:
Seneca Weekly Courier – 4 Jul 1879, page 5
June 3, 1879
Contract awarded to P. J. Pauley & Bro. to build jail according to plans and specifications on file, for the sum of $9,943. Bond of contractors approved.
5 Sep 1879
The steel-clad cells to the new jail are being put in this week, and the building will soon be ready for use. To those who have been used to seeing large jails, built of massive stone, and covering a large space of ground, the new jail at Seneca looks small; but it embraces all late improvements for the safe-keeping of convicts, compactly built; and although $10,000 seems-a big price, we are satisfied when the new jail is in use, the people will appreciate the advantages of the building,, and acknowledge the County Board did a wise thing in the selection made. If you don’t think the jail a good one, get into a cell and try and got out. You will then “know how it is yourself.”
Seneca Weekly Courier – 5 Sep 1879 – page 8
Pauly patent on first floor jail cells
24 Sep 1879
The New Jail. The finishing touches are this week being put on the new jail The edifice is a brick structure, with a two story front and L. The building is situated on the block immediately in front of the school house, and presents at first sight more the appearance of a handsome dwelling than a jail The main building is 32×20 feet in size, contains six rooms and is conveniently arranged The L. for the rest of the jail. The jail is 22×20 feet, and contains the cells. There are three in number, each with ample accommodations for four prisoners. They are of steel, and of the celebrated Pauley patent, which are said to be the strongest made, and for sanitary arrangements are very perfect. In addition to this department, another occupying two of the upper rooms of the jailor’s residence has been arranged with a view to the confinement of lady prisoners and such as are detained on slight causes, and for only a limited time The premises are provided with a large cistern, and the building furnished with water works. In short, the whole building is a model of beauty and convenience, but it costs Nemaha county $9,965 to It claims to having the handsomest jail in northern Kansas
9 Oct 1879
A MODEL PRISON.
Brief Description of the New
Nemaha County Jail.
The Work All Completed and the Building Received by the Commissioners.
On Wednesday of last week the new jail at Seneca was formally received by the Nemaha county commissioners. It is a model of neatness, and all who have visited it pronounce its interior arrangements perfect. The building presents a very attractive appearance, the exterior walls being built of brick and handsomely ornamented. The main structure is two stories high, the front portion being designed as the jailer’s residence, and the rear extension arranged as a prison. The most attractive feature, however, is the construction of the cells. They are made on the plan of Pauly’s celebrated patent steel- clad jail cells. There are three of the cells, each capable of accommodating four prisoners, and all provided with hammocks and bunks, giving them a look that would seem inviting were the formidable bolts, and bars removed. The cells are arranged in a row, with excellent means of lattice ventilation at the rear, while in front is a corridor, separated from the outer corridor by open lattice-work, all made of the famous patent hardened steel, that defies files, saws, or cold chisels. The entire top and bottom, all the outer walls of the cells, the rear end of the corridor and the partition between the corridor and cells are made of plate work, hardened by the best processes known, and are absolutely saw and file-proof. The sanitary arrangements are the most thorough that could be desired, the lattice work and the foul air ducts affording ample ventilation, while the water closets, water tank, pump, hose, supply-pipe, soil-pipe, etc., enable the jailer to always keep his prison clean. This system of constructing jails contains three main points of superiority over all others, viz.: Security of pris-
oners from escape, sanitary arrangements and safety of the jailer in hand- ling prisoners. All but the latter have been briefly mentioned above, and this would be difficult to describe. In the main (or jailer’s) corridor near the entrance to the prisoners’ corridor that laces the cells, is a strong box, made of hardened steel. To open the cell doors the jailer enters the corridor and re- moves the padlocks; then retires, closes and locks the corridor door. He than removes the padlock from the lever (in the lever box), and pulls the lover which slides the locking bars and releases all the cell doors. In locking up at night the prisoners step into their cells, closing the doors. The jailer pushes the lever back and locks it; then opens the corridor door, goes in and places a pad- lock on each cell door; retires and closes the corridor door, locking it at top and bottom, then closes the lever box, locking it with the combination lock. Thus it will be seen that the jailer never needs to come in contact with the prisoners, and hence is secure from attack. The arrangement is so simple and so easily operated that a lady, or even a child can handle the prisoners with perfect safety. The jailer’s apartments are models of neatness, and upstairs are two rooms with gratings, both neatly furnished, and designed for female prisoners, in- sane persons or others who may be temporarily confined. The whole structure cost less than ten thousand dollars, and Nemaha county, with her characteristic punctuality paid the cash on delivery, and the builders, Messrs C. L. Wundi & Co. of Burlington, Iowa, agents for P. J. Pauly & Bro. left at once for Massachusetts. where they have a contract to construct another prison on the same plan. Our people consider that they have made a very profitable investment.
Seneca Tribune – 9 Oct 1879, page 1
26 Feb 1904
HENDERSON BROKE JAIL.
Man Under Arrest For Goffs Robbery Digs Out and Escapes.
Henderson, the man arrested at St. Joseph some time ago and brought back for trial on charge of having burglarized the bank at Goffs, made his escape Tuesday evening by digging his way through the brick walls of the county jail and is still at large. Sheriff Camp- bell and County Attorney Nold went to St. Joseph Tuesday morning and put in the day with the police of that city, looking for evidence against Henderson, to be used at his trial, which was to have come on at the approaching term of court. Henderson evidently thought the absence of the Sheriff a good opportunity to make his get-a- way. In the absence of Mr. Campbell, the jail and prisoners are in charge of Mrs. Campbell, who is also deputy. Most of our readers understand that the cells of the jail consist of a steel cage in the center. Around this is a corridor into which prisoners may be turned for exercise. This corridor is only enclosed by the brick walls of jail, with iron bars over the jail windows. It was not intended for the confinement of prisoners who had any great motive for attempting escape, the steel cage being provided for these.
The prisoners in the jail besides Henderson were Ellsworth, the Nebraska man put in last week for eloping with another man’s wife, Bert Hebert, the young fellow with the Ellsworth-Bhug art outfit, and Thomas Porter, who is in for contempt of court. These with Henderson were in the corridor of the jail during the day. The supper for the prisoners was later than usual Tuesday evening. This was handed in to them about seven o’clock, and was eaten in the corridor, as is the custom. Henderson was there and ate supper with the others. Some time about eight o’clock Mrs. Camp- bell went to the jail door to take away the dishes and lock the prisoners into the cells for the night, and it was then discovered that Henderson was missing. Investigation showed that he had cut his way through the brick wall of the jail in one corner, making an opening just large enough for a man’s body. The other prisoners certainly could not but have known what was going on when he was working his way through the wall, but they all profess ignorance and refuse to tell anything about it. An alarm was given as soon as Henderson’s absence was discovered, but there was no clue to the direction he had taken and searching for him then was like looking for the proverbial needle in the hay stack. County Attorney Nold was on his way home from Mt. Joe and where he arrived at ten o’clock assisted in the matter. The authorities decided that the best plan would be to send for the Beatrice blood hounds and this was immediately done. The hounds arrived here just before dinner Wednesday, and after dinner were taken to the jail and put on the scent, the jail premises meanwhile being guarded to prevent spectators from obliterating the trail. The dogs soon made a start from the hole in the jail wall, went over the northeast corner of the high fence, through the barnyard and along the alley and streets to the Grand Island crossing just east of the Gilford Hotel there they seemed bothered. They then went out along the wagon road past the John Simon place, but lost scent and were brought back still started again. This time they took to the railroad track and followed it straight into Oneida. Here they went through the town, making a stop at the store of Mrs. Magee, where there was evidence of an attempt at breaking in. The store had not been entered however. It is surmised that Henderson was here and thought it a good chance to get a change of clothing, but was either frightened away or at that time heard his train coming. From the store the dogs went to the depot, which was the end of the trail, the man having evidently taken the morning train for the east. No farther trace of the escaped man has been found. A few days before Henderson’s escape he was shaved, his hair cut and his picture taken. This may assist in locating him. He was evidently a smooth criminal, a genuine specimen of the crook species, used to working his way out of jail with limited facilities. The only tools he had to cut through the jail wall were a piece of iron used for a stove poker, and a piece of the bail to a bucket; He may have had outside help, but not necessarily so, as it would be but a short job for one man to work out the mortar from between the bricks of the wall and then remove the brick. In the mean time there is no great loss without some gain. If he is not captured Nemaha county will be saved an expensive trial in court.
Courier Democrat – 26 Feb 1904, page 4
23 Aug 1906
Jail Delivery. Joe King, in jail for stealing the team of Thomas Donahue on Coal Creek, and a man named Thompson, in custody for burglary at Goffs, broke out of jail after dark Wednesday evening by going through the roof and made their es- cape. At 11 o’clock p. m. Sheriff Den- nis and deputies are driving the country in pursuit.
Courier Democrat- 23 Aug 1906, page 4
12 April 1906
For A New Jail.
The county commissioners of Nemaha county have practically decided to build a new jail. The necessity of this is past argument. The old jail is not only insecure for the keeping of prisoners, but is in a very unsanitary condition and cannot be bettered, except by building anew. The matter has been under advisement for over a year past, but the commissioners entertained a doubt as to their authority to build without submitting the matter to a vote. However it has been decided upon the counsel of both County Attorney Her- old and Judge Stuart that they have such authority. They have had drawn plans of such a jail as it is contemplated to build. The plans were made by the Pauly Jail Building Company of St. Louis, who are specialists in this line. The building would be two stories in height. The first floor will be divided into two sections, separated by a brick wall. On each side of this wall will be three steel cages or cells and a bath cell. On the upper floor will be two cells and room for additional cells or a sleeping room for the jury. The sheriff’s office will be in front, and in the front corridor will also be two additional cells, one on each floor. All cells can be locked and unlocked from this corridor. The building will be furnished with toilet necessaries and bath tub and heated by steam. The plans pro- vide for a modern and complete jail building, such as would provide for the needs of the county in that line for generations to come. To build with any other idea in view would be foolish economy.
Courier Democrat – 12 April 1906 page 6
23 Aug 1906
Jail Delivery.
Joe King, in jail for stealing the team of Thomas Donahue on Coal Creek, and a man named Thompson, in custody for burglary at Goffs, broke out of jail after dark Wednesday evening by going through the roof and made their escape. At 11 o’clock p. m. Sheriff Den- nis and deputies are driving the country in pursuit
Courier Democrat – 23 Aug 1906 page 4
30 Aug 1906
The County Commissioners meet in Seneca September 3rd to settle the question of building a new county jail. A representative of the Pauly Jail Co., will be there and submit plans. The commissioners want to purchase plans and build the jail as they see fit.
Corning Gazette – 30 Aug 1906, page 8
6 Sept 1906
The county commissioners were in session the first of the week, to meet a representative of the Pauly Jail Building Company, to consult concerning plans for the new county jail. The commissioners have practically determined that the jail is to be built, and are now laboring with the details of plans and price.
Courier Democrat, 6 Sep 1906, page 5
Pauly patents on 2nd floor jail cells
25 Oct 1906
The Board met and opened bids as advertised for new County jail and found bids as follows: Shaul & Assenmacher bid for completion of jail $10,658.00, Vorhes & Son on building etc $4,691.45 and Pauly Jail Co. on steel work, etc. $6,202.00, and thereupon the Board postponed further consideration of all the bids until a special meeting of the Board to be held on November 10th,1906.
Seneca Tribune – 25 Oct 1906, page 5
18 April 1907
The county commissioners have advertised for bids for a new county jail. They met with a citizens committee on Friday, composed of A. L. L. Scoville W. H. Smith and G. W. Williams, who went over the premises with them carefully and agreed with the board that conditions demanded a new jail. The residence will be enlarged and the jail proper will be two stories high. Both will be strictly modern throughout. At present Nemaha county has only one prisoner in the county jail, C. S. Backaday, who is there because the jury failed to agree at the March term of court.-Seneca Courier.
Corning Gazette – 18 April 1807, page 8
2 May 1907
[First published April 18, 1907]
Notice to Contractors. Sealed bids will be received at the office of the county clerk of Nemaha county, Kansas, at Seneca Kansas, at any time on or before May 20, 1907, up to 3 o’clock p. m. for repairing the Nemaha county jail according to plans, specifications and details prepared by John Y Benfer, architect, now on file at the above named office, and may be examined there. All bids must be accompanied by a certified check of $250.00 as a guarantee that the bidder will sign contract and furnish good and sufficient bonds, which will be returned to the unsuccessful bidder. An acceptable assurity company or individual bond for one- third of the amount of the contract price will be required of the successful contractor. The award will be made known by the county commissioners ten days after the bids are opened, unless they deem it necessary to further investigate the standing of the contractor. All bids will be opened in the commissioner’s room at the courthouse May 20, 1907, at 3:30 o’clock p. m. Address all bids to E. S. Randel county clerk The Board of County Commissioners re- serves the right to cancel and reject any and all bids.
E. S. RANDEL, County Clerk,
Seneca Tribune – 2 May 1907, page 5
23 May 1907
The board of county commissioners were in special session. Monday, to consider the bids for the new jail The bids were opened and further consideration taken until tomorrow Shaul & Assenmacher and Vorhes & Son were the only bidders.
Seneca Tribune – 23 May 1907, page 2
5 Dec 1907
The Sheriff in Jail
First of the week Sheriff Dennis took up his quarters in the new jail, and is at home all callers of whatever station or degree. The new carpets, furniture and furnishings give its former dull surroundings a touch of pleasure and comfort, and the chief peace officer of the county has reason to feel a little puffed up over the change.
Seneca Tribune – 5 Dec 1907, page 3
13 Jan 1955
The jail residence is undergoing some repairs and redecoration before the Petersons move into it as a home. Dale Miller is busy on plaster and paper, and Stalcup and Jeanneret on some floor work. The residence part of the jail building is showing structural defects that appear as quite a problem. South wall, over which weight of the cupola rests, is pulling outward.
Courier Tribune – 13 Jan 1955,page 1
7 April 1955
ALONG THE NEWS FRONT
Jail Cupola Coming Off In Repair. Job
Nemaha county’s jail, the-office and residence part, has been showing some bad structural damage, with the south wall pulling out. A repair job is now under way. The heavy cupola, which has put a lot of weight on the wall, is being taken off, and the wall will be rebuilt and the roof line leveled.